Construction Intelligence Brief
Estimating is a forecast, and forecasts can be scored. Reviewing how past estimates compared with results shows the bias to correct before the next bid.
When we estimate a job, how close do we usually come?
Many contractors learn from individual surprises but never score their estimates across the whole portfolio. Without a record, bias persists: bids that are consistently too low in some trades, too optimistic on productivity or too slow to reflect price increases.
Scoring a few years of estimates against actual results is usually the highest-value analysis a contractor can do on its own data.
An estimating accuracy review includes:
The aim is to separate bias, which can be corrected in the next estimate, from noise, which needs a contingency.
In the synthetic contractor, Calculated the estimated final margins for the six in-progress projects moved between the two snapshots by 1.5 pts down at Riverside, 7.0 pts down at Harbor, 6.5 pts down at Maple Street, 2.0 pts down at City Hall, 1.0 pts down at Eastgate, and 2.0 pts up at Valley School. The average change is about 2.7 points down.
Calculated Five of six projects moved the same way. That pattern is more like bias than random noise, and it matches a portfolio whose gross margin fell from 8.5% to 5.6%. The spread is also wide, from a gain of 2.0 points to a loss of 7.0, so a contingency would be needed even after the bias is corrected.
Hypothesis Since cost per labor hour rose 7.7% over the period, part of the bias may be labor inflation after the bids were priced. Information gap The demo does not show each project’s variance by cost type. A review that does so for completed jobs would show whether labor, materials, subcontractors or scope drove the misses.
4. Explore the interactive experience
Project Performance Dashboard: a project portfolio dashboard with estimated final margins, a scenario simulator for change orders and costs, evidence-linked answers from APIS, and a sample brief, all on synthetic data.
The experience below is built on a synthetic contractor, “Demo Builders Inc.” It has no bid history or backlog data, so its in-progress projects are used to show the method. Nothing in it is real.
Accuracy improves with a feedback loop between results and estimates.