Construction Intelligence Brief
Labor is the cost most affected by how well a job is run. Revenue and cost per labor hour show whether each hour is earning more or less than before.
Is each hour of labor on our jobs earning as much as it used to?
Labor cost can rise because wages rose or because crews take more hours to do the same work. The first is a price change and the second is a productivity change, and they call for different responses.
Watching revenue per labor hour next to cost per labor hour is a compact way to see whether productivity and pricing are keeping up with wages.
Productivity measures work at several levels:
A fall in margin per hour means wages and costs are rising faster than the pricing and output that cover them.
In the synthetic contractor, Calculated labor hours grew 7.1% to 180 thousand. Revenue per labor hour rose from $274 to $286 (4.5%), but cost per labor hour rose from $251 to $270 (7.7%).
Calculated The gap between them, the margin per hour, fell from about $23 to about $16, a drop of roughly 30%. Total labor cost rose 17.7%, faster than hours at 7.1%, which means each hour cost more.
Hypothesis Because cost per hour includes materials, subcontractors and other costs spread over hours, a fall can come from several lines, not labor alone. Information gap The demo has no crew-level hours per unit of work, so it cannot separate wages from productivity. In the scenario, a 1% rise in labor cost per hour lowers gross profit by about $146K, while a 1% gain in revenue recovery adds about $515K.
4. Explore the interactive experience
Project Performance Dashboard: a project portfolio dashboard with estimated final margins, a scenario simulator for change orders and costs, evidence-linked answers from APIS, and a sample brief, all on synthetic data.
The experience below is built on a synthetic contractor, “Demo Builders Inc.” Nothing in it is real, so you can explore freely.
Improving productivity is slow work, but it pays on every job.