Construction Intelligence Brief
A contractor can report healthy revenue and profit and still run short of cash. Revenue is recognized as work progresses. Cash arrives when owners pay.
We are growing and profitable on paper. Why is cash tight?
Construction accounting recognizes revenue as work is done, usually by percentage of completion. Billing and payment follow a different schedule, often with retainage and approval delays. The gap between the two is where cash problems arise.
Looking at the income statement alone, a contractor can be overconfident. Looking at cash alone, it can miss profit problems. Both views are needed.
Examining the two side by side takes a few measures:
Underbilling means cash has been spent for work not yet billed. Overbilling means cash was collected ahead of work, which can be a source of funds or a hidden liability.
In the synthetic contractor, Calculated revenue recognized grew 12.0% to $51.5M, but gross profit fell from $3.90M to $2.90M. Growth in recognized revenue came with falling margins.
Illustrative An illustration, with invented numbers, shows how the gap forms. On a $10 million project that is 50% complete, revenue recognized is $5 million. If the contractor has billed only $4 million, there is $1 million of underbilling: costs were paid, revenue was recognized, and the cash has not come in. Add retainage withheld by the owner and the gap widens.
Calculated The portfolio is also mid-stream: Maple Street Apartments is 71.0% complete after growing recognized revenue 43.0%, and Harbor Logistics Warehouse is 64.0% complete. Information gap The demo has no billing or collection data. Comparing recognized revenue with billings and collections on each project is the check to add.
4. Explore the interactive experience
Project Performance Dashboard: a project portfolio dashboard with estimated final margins, a scenario simulator for change orders and costs, evidence-linked answers from APIS, and a sample brief, all on synthetic data.
The experience below is built on a synthetic contractor, “Demo Builders Inc.” Nothing in it is real, so you can explore freely.
Managing the gap means watching billing, collections and terms, not only profit.